Sydney Yard Access Bridge

Scope

The Sydney Yard Access Bridge project was the first early and enabling works package of the NSW Government’s Sydney Metro City & Southwest project.

The 130m long bridge crosses five intercity lines that had never been closed under a single possession. While a full closure was planned, the main girders and cross girders were installed within the 54-hour possession window.

CJC role

Sydney Metro recognised the significant risks during the proposed possessions, when erection of the bridge was planned over the intercity railway lines. CJC was engaged during the construction phase to provide a peer review of the construction methodology and associated temporary works required to erect the bridge. In addition, our team provided on-site supervision and support for Sydney Metro during possessions.

 

CJC worked collaboratively with Sydney Metro and Laing O Rourke to review all drawings, methodology and program, providing advice on risk mitigation measures while making suggestions to improve the possession program. CJC also visited the fabrication workshop during trial assembly and provided technical advice to Sydney Metro regarding the 130m long bridge.

GUIDING YOUR PROJECTS TO SUCCESS WITH DECADES OF EXPERIENCE 

Our Experts, exceptional results

Combining decades of experience to deliver exceptional project management & construction solutions, ensuring your projects are completed on time, within budget and to the highest standards of quality & safety.

Jonathan Davies

Project Manager

other related PROJECTS

Explore our portfolio of related projects, showcasing CJC’s expertise across diverse sectors.

From infrastructure to asset management, each project highlights our commitment to innovation, quality, and delivering solutions tailored to client needs.

Download PDF

Fill in the form below to download your copy of our General Capability Statement.

General Capability Form