Great Western Highway, NSW
Scope Transport for New South Wales has engaged CJC Management to provide constructability advice to the Great Western Highway Upgrade East Project. The Project is made up of two sections, namely Katoomba to Medlow Bath and Medlow Bath to Blackheath. It is understood that the current intention is for the K2M and M2B sections to […]
Sydney Gateway Program Peer Review
Scope The Sydney Gateway Project comprises new and upgraded road and rail infrastructure located at the Sydney Airport and Port Botany precincts. This new infrastructure will improve freight capacity on the Port Botany rail line and link WestConnex to Sydney Airport and Port Botany; Australia’s two largest international gateways. The review focuses primarily on construction […]
Stockton Bridge Half Joint Rehabilitation
Scope Stockton Bridge is located over the north arm of the Hunter River, near Newcastle in NSW. Built in 1971, it is a concrete box girder bridge with an overall length of 1,023m. In 2007, the bearings were replaced in the two half-joints and monitoring of the structure has continued since. From 2016, a design […]
Sydney Harbour Bridge Arch Maintenance Units (AMU)
Scope RMS (now TfNSW) is proposing the replacement of the four existing Arch Maintenance Units (AMU) on the Sydney Harbour Bridge. The dated AMUs are to be replaced with new infrastructure consisting of two cranes at each end that span between the top chords of the bridge. The works are needed to provide safe […]
Sydney Harbour Bridge Step Free Access
Scope As part of the Sydney Harbour Bridge Step Free Access project, Roads and Maritime Services (RMS) carried out extensive work to investigate preferred locations for lift access. Considerations included the heritage value, accessibility standards, visual impacts and integration with the existing structure. Following this work and completion of the project, the lifts now provide […]
WestConnex Stage 1A M4 Widening
Scope WestConnex Stage 1 M4 Widening involved building an additional lane in each direction on the M4 Motorway, between Parramatta and Homebush. The project is approximately 7.5km long. The responsibilities of our team included implementation of risk management project controls, project preparation and readiness, interface management with utilities providers and stakeholders, review of the design against […]
Sydney Yard Access Bridge
Scope The Sydney Yard Access Bridge project was the first early and enabling works package of the NSW Government’s Sydney Metro City & Southwest project. The 130m long bridge crosses five intercity lines that had never been closed under a single possession. While a full closure was planned, the main girders and cross girders were […]
Australia Avenue & Homebush Bay Drive Intersection Upgrade
Scope Transport for NSW (TfNSW) is proposing to upgrade the intersection of Australia Avenue, Homebush Bay Drive and Underwood Road. This roundabout is one of the four gateway intersections providing access between the arterial road network and the Sydney Olympic Park precinct. The idea of relocating an existing Homebush Bay Drive pier was proposed to […]